2015

PROJECT DETAILS
41mw (33 and 8mw) co-generation power plant, 4nos 12ton Induction Furnaces and SMS, 160ton submerged electric arc furnace for ferro alloys. 700tpd SIP sponge iron and Pellet plant. 35tph TMT-8-32mm/WRM-5.5mm plant.
RESULTS ACHIEVED
Troubleshooting analysis carried out for 41mw power plant tripping and blackout issues and frequent electrical and electronic failures with IF, Ferro Alloy, SIP and Pellet and wire rod mill sections.