Zero sequence harmonic filter

Honeywell Technologies, Bangalore

2003 -2010, Repeat jobs.

PROJECT DETAILS
Three facilities for Avionics systems, product developments and Software Development.
RESULTS ACHIEVED
Facing equipment tripping and failures. Designed and implemented Earthing Grid System for the facility's data center for solving Avionics lab's chronic electronic failures.

EID Parry India Ltd, Corporate bldg

Chennai, A 1932, 6story, 250,000Sq.Ft. heritage building. 2012- 2017. Repeat jobs.

PROJECT DETAILS
Head Office of Murugappa conglomerate that accommodates 1300 employees. Local Utility mandated harmonic limits. In-addition was facing failures with air conditioning compressor motors, transformer, Lighting ballast failure, computer cards and SMPS.
RESULTS ACHIEVED
Installed 750A and 646A tuned harmonic filters and that resolved all harmonic failures and limited harmonic distortions within CEA 2007 and IEEE 519 norms of local the utility.