Power Quality Analyser

The Energy Research Institute, Bangalore

1998-1999, Repeat Jobs.

PROJECT DETAILS
A R&D Institute for Energy Conservation and Power Management.
RESULTS ACHIEVED
On behalf conducted troubleshooting, Power Quality and Harmonic Analysis studies at JK White Cements, Gotan, Rajasthan. Supplied Power Quality Analyser.

Central Power Research Institute Bangalore

2001 -2005

 

PROJECT DETAILS
A R&D Research Institution - Third party testing and verification. Supplied 2sets Power quality analyzers
RESULTS ACHIEVED
On behalf conducted troubleshooting, Power Quality and Harmonic Analysis studies for Ispat Industries Limited Dolvi and Tata Iron and Steel Company Limited TISCO at Jamshedpur.

Ispat Industries Ltd, Dolvi Maharashtra

2001 -2006, Repeat jobs.              

 

 

PROJECT DETAILS
Electric Arc Furnace 2x 180 Ton, 150mva, 33kv/ 1120v transformer, 2x 2000A SF6 CB with Siemens, Germany make 2x 190mvar SVC with TCR, 50mvar 2HF, 30mvar 3HF, 30mvar 4HF, and 70mvar 5HF. Main I/C 4x155mva, 220/33kV, Ynynd1-tertiary for resistive earthing.
RESULTS ACHIEVED
Root cause analysis for chronic SVC reactors and capacitor failures. Upstream 5000TPM Blast Furnace and SIP and Downstream Hot rolled mill and DRI sponge iron plant. 3rd party testing.

Sarda Energy & Minerals Ltd. Raipur

2013- 2016, Repeat jobs.
 

PROJECT DETAILS
96mw (3nos 32mw) co-generation Power Plant, 4sets 15ton 7.2mva Induction Furnaces. 5sets 9mva submerged electric arc furnaces, 250tpa sponge iron plant. 10mva, 30tph wire rod mills. 250tps pellet plant.
RESULTS ACHIEVED
Troubleshooting analysis for 3x32mw power plant tripping and blackout issues. Root cause analysis for mis-rolling in the wire rod mill at high rolling speed.

Hi-Tech power and steel, Raipur

2013, Chhattisgarh

PROJECT DETAILS
10mw Co Generation power plant and 30ton induction furnace and TMT bar rolling mill.
RESULTS ACHIEVED
Troubleshooting analysis for the hunting and tripping of 10mw power plant. Solution directions provided. Supplied Energy Analyser

Suryadev alloys & power, Gummidipoondi

2013 Chennai

PROJECT DETAILS
80mw 2sets thermal power plants with air-cooled condensers. SEC=0.75ton/mw of coal, PP Aux=8%; 2x330tph boiler, 95kg/cm2, 540oC.
RESULTS ACHIEVED
Trouble shooting study carried and and report with recommended measures submitted.

Nestle India Ltd

1997, New Delhi

PROJECT DETAILS
Milk products and food processing
RESULTS ACHIEVED
Energy management system

Bottlers Nepal (Terai) Ltd, Nepal

2014, Bharatpur

PROJECT DETAILS
RGB 21500bph and PET 20000bph Lines. Was facing tripping and failures with PET SIDEL machine.
RESULTS ACHIEVED
Power quality and harmonic analysis carried out and report with recommendations submitted.

BHEL Libya Project

1998

PROJECT DETAILS
Power sector project
RESULTS ACHIEVED
Supplied data logger