Hotel

The Residence Belle Mare, Mauritius

2010

PROJECT DETAILS
163 rooms Luxury Leisure hotel with 295,000sqf area, 4floors (1B+1G+2) and 0.87mw maximum demand
RESULTS ACHIEVED
5% Energy Savings verified at NO-COST implementation

Taj West End Hotel Bangalore

1997 -2004, Repeat jobs.

PROJECT DETAILS
Screw Chiller efficiency test. BMS efficacy testing.
RESULTS ACHIEVED
Energy and total power management. Harmonic distortion correction.

Taj Samudra Colombo, Sri Lanka

2005

PROJECT DETAILS
320 Rooms, 494,000SQF built-up area, 500tr centrifugal air conditioning system and 1.9mw maximum demand.
RESULTS ACHIEVED
Energy and total power management

Taj Vivanta Hotel Bangalore

1997 -2006

PROJECT DETAILS
167 rooms 178,600SQF built-up area, 0.80mw maximum demand.
RESULTS ACHIEVED
7% Energy Savings verified at NO-COST implementation. Efficiency testing for screw chiller. BMS testing. Installed Harmonic Filter. Solved tripping of centrifugal chiller on grid voltage fluctuations.

Taj Gateway Hotel Bangalore

1997-2004, Repeat jobs.

PROJECT DETAILS
Third party test Screw chillers efficiency test. BMS efficacy test.
RESULTS ACHIEVED
9% Energy Savings verified at NO-COST implementation

Taj Exotica Bentota, Sri Lanka

2005

PROJECT DETAILS
162 Rooms, 220,000SQF built-up, area 2x200tr Centrifugal chillers, 0.8mw maximum demand at 70% occupancy
RESULTS ACHIEVED
Energy and total power management

Taj Airport Garden Negombo, Sri Lanka

2005

PROJECT DETAILS
120 Rooms. 86,700SQF built-up area, 180TR Reciprocating chiller, 0.50mw maximum demand at 80% occupancy
RESULTS ACHIEVED
Energy and total power management

Oberoi Hotel Bangalore

2004

PROJECT DETAILS
Trouble-shooting UPS cards, Computer SMPS and Monitor Failures
RESULTS ACHIEVED
Eliminated reported failures by implementing recommended solutions.

Mercure Homestead Residences, Accor Hotels, Bangalore

2010

PROJECT DETAILS
Air cooled air conditioning system installed. 126 rooms, each between 400 -854 sft size, 125,000sqf built-up area including inc.12% park&M.
RESULTS ACHIEVED
6% Energy Savings verified at NO-COST implementation